Stage 2 Bridge Substructure Complete
Dunnet Bay Construction has completed construction of the Stage 2 bridge substructure and are currently working on the Stage 2 bridge superstructure. The Stage 2 bridge superstructure is expected to be poured the week of November 18th. The contractor is concurrently working on constructing roadway pavement on Washington Street, north and south of the bridge, as well as on Aurora Avenue, west of Washington Street.
Percent Completion = 63%