Bridge Foundation Construction
Dunnet Bay Construction has installed the temporary soil retention system at the north abutment stageline and NE retaining wall and demolished the Stage 1 portion of the existing Washington Street Bridge and NE Retaining Wall. Abitua Sewer, Water, and Plumbing has installed the new 10” PVC sanitary sewer along Chicago Ave and installed inserting valves on the existing watermain along Washington St and Chicago Ave. Geneva Construction paved the sanitary sewer trench and inserting valve patches along Chicago Ave. Dunnet Bay Construction has also began constructing the Stage 1 drilled shafts at the Stage 1 Pier, North Abutment, and NE Retaining Wall. In the coming weeks, Dunnet Bay Construction plans to continue constructing the Stage 1 portion of the bridge and install the utility crossings through the river.