Stage 1 Cofferdam to Divert the DuPage River Installed
Dunnet Bay Construction has installed the Stage 1 cofferdam to divert the DuPage River through the south span of Washington Street Bridge. Dunnet Bay has begun installation of the temporary support system under the bridge, which is expected to be completed on Friday, May 5th. Washington St is scheduled to be switched into Stage 1 on Tuesday, May 9th, shifting all traffic onto the west side of the bridge. Once traffic has been shifted, the contractor plans to begin Stage 1 removal of the existing bridge.
Percent Complete = 5%.