Substructure In Progress
Dunnet Bay Construction has constructed the Stage 1 portion of the North Abutment and the NE Retaining Wall. They have also began construction of the Stage 1 portion of the North Low Flow Walk. Next, Dunnet Bay Construction plans to complete the Stage 1 portion of the North Low Flow Walk and begin construction of the Stage 1 Pier Cap as well as Stage 1 falsework for the bridge deck.
Percent Completion = 22%