Traffic Configuration Changes
Traffic was switched into Stage 1 Maintenance of Traffic (MOT) on Wednesday, May 10th per the map below.
The contractor has removed the Stage 1 portions of the north and middle spans of the Washington Street Bridge. Next, they will install the temporary soil retention systems along the stageline and the northeast wingwall in order to begin construction of the bridge.
Percent completion = 7%.